Gantt Chart for Angular

AngularData visualization

A project schedule: a task tree grid (name, start, end, duration, progress, resources, float) beside a timeline of bars with summary tasks, milestones, progress, baselines, dependency connectors, the critical path, non-working days, and today. Tasks are scheduled in working days of a Business Calendar: dependencies (finish-to-start, start-to-start, finish-to-finish, start-to-finish, with lag or lead) push successors later, never before their requested start; manual tasks keep their start and report violated dependencies. Editing: drag a bar to move it, its end to resize it, its link handle onto another bar to link them; Ctrl/Cmd+Left/Right moves by a working day, Shift+Left/Right changes the duration, and the toolbar offers the same plus Link (then Enter on the successor). Every change is dispatched first as the cancelable aui-task-change with the tasks, dependencies, and new schedule; changes are undoable. An optional resource histogram shows daily load against capacity. Rows are virtual. The engine (scheduleGantt, resourceLoad, createsCycle) is pure and runs without DOM (for example on a server).

  • DependenciesDependent tasks follow when a task moves, counted in working days.
  • Business calendarWorking days and holidays drive durations and the schedule.
  • Critical pathHighlight the tasks that decide the end date, and compare with baselines.
  • Resource loadAssign people with units and see their load as a histogram.
  • Drag or keyboardMove and resize tasks by pointer or keyboard, with undo and redo.

Behavior, design tokens, and limitations are described on the Gantt Chart page; this page covers the Angular API.

import { Component } from '@angular/core';
import { plainDate } from '@absoluteui/core';
import type { GanttTask, GanttTaskChangeDetail } from '@absoluteui/components/gantt';
import { AuiGantt } from '@absoluteui/angular/gantt';
@Component({
selector: 'app-plan',
imports: [AuiGantt],
template: `<aui-gantt label="Plan" [tasks]="tasks" [editable]="true" scale="day" (taskChange)="changed($event)"></aui-gantt>`,
})
export class PlanComponent {
tasks: GanttTask[] = [{ id: 'a', parentId: null, label: 'Kick-off', start: plainDate(2026, 10, 5), duration: 1 }];
changed(detail: GanttTaskChangeDetail): void {
this.tasks = detail.tasks;
}
}
Terminal window
npm install @absoluteui/angular @absoluteui/components @absoluteui/core @absoluteui/theme

Setup with provideAbsoluteUI() is covered in Getting started. Styles are included with the component.

import { AuiGantt } from '@absoluteui/angular/gantt';

Defaults for every instance: provideAbsoluteUIConfig({ components: { gantt: { ... } } }) (see Configuration).

Class AuiGantt; template reference #ref="auiGantt".

Server rendering: Renders on the server; the browser re-creates it after hydration.

Input Type Default Description
label string Required. Accessible name of the tree grid; the toolbar is named ‘{label} controls’. Non-empty.
resources readonly GanttResource[] { id, label, capacity? (percent per working day, default 100) }; assignments must reference them.
calendar BusinessCalendarDefinition Working days, holidays, and exceptions (default Monday to Friday). Durations and lags count its working days; non-working days are shaded.
editable boolean false Pointer, keyboard, and toolbar editing (move, resize, link).
columns readonly GanttColumnKey[] '['name', 'start', 'end', 'duration']' Grid columns: ‘name’ first, then any of ‘start’, ‘end’, ‘duration’, ‘progress’, ‘resources’, ‘float’ (unique).
showCritical boolean true Mark critical tasks (badge, hatched bar, red connectors).
showBaselines boolean true Draw baselines and describe baseline variance in the grid.
showHistogram boolean false Show the resource load histogram below the chart (needs resources): daily load per resource with peak and over-capacity days as text.
today PlainDate Date of the today line and the Go to today button (default: the device’s local date).
canEdit (task: Readonly<GanttTask>) => boolean Veto edits of a task (also as a link successor). Summary and read-only tasks are never edited.
rowHeight number '36' Row height in CSS px (24..96). Rows have a fixed height (virtual rows).
historyLimit number '50' Undo depth (0..500).
locale string 'en-US' Dates, numbers, the first day of the week (week scale), plural forms, and messages.
direction Direction 'ltr' Mirrors the timeline and swaps ArrowLeft/ArrowRight.
Model Type Change output Description
[(tasks)] readonly GanttTask[] (tasksChange) Tasks: { id, parentId (summary task id or null), label, start (requested start, PlainDate), duration (working days, 0 = milestone), progress? (0..100), manual?, assignments? ({ resourceId, units? percent }), baseline? ({ start, end } inclusive), color? (1..8), readOnly?, collapsed? }. Tasks with children are summary tasks (their start and duration are ignored). Order within a parent is the array order. Validated (GANTT_OPTIONS). Replacing it clears the undo history.
[(dependencies)] readonly GanttDependency[] (dependenciesChange) { id, from (predecessor), to (successor), type? (‘FS’ default, ‘SS’, ‘FF’, ‘SF’), lag? (working days, negative = lead) }. Leaf tasks only, one per pair, no cycles (the error names the cycle).
[(scale)] GanttScale (scaleChange) Timeline scale (32, 16, or 5 CSS px per day); also changed by the zoom buttons and setScale().
Output Payload Description
(taskChange) GanttTaskChangeDetail Before a change is applied; preventDefault() keeps the previous state. Re-emits aui-task-change.
(taskActivated) GanttTaskActivateDetail Enter on a row. Re-emits aui-task-activate.
(expandChange) GanttExpandChangeDetail A summary task was expanded or collapsed. Re-emits aui-expand-change.
Property Type Description
canUndo Signal<boolean> A change can be undone.
canRedo Signal<boolean> An undone change can be redone.

Call them through a viewChild query or a template reference.

Method Description
setScale(scale: GanttScale): void Change the scale, keeping the first visible date; emits aui-scale-change.
setExpanded(id: string, expanded: boolean): void Expand or collapse a summary task (emits aui-expand-change).
expandAll(): void Expand every summary task.
collapseAll(): void Collapse every summary task.
scrollToTask(id: string, options?: { focus?: boolean; } | undefined): void Expand the ancestors, scroll the row and bar into view, and focus the row (unless focus is false).
scrollToDate(date: PlainDate): void Center the timeline on a date.
focusTask(id: string): void scrollToTask with focus.
moveTask(id: string, start: PlainDate): boolean | undefined Change the requested start (next working day). Emits aui-task-change; false when refused or cancelled.
setDuration(id: string, duration: number): boolean | undefined Change the duration in working days (0 = milestone).
addDependency(dependency: GanttDependency): boolean | undefined Add a dependency (validated; throws GANTT_OPTIONS for cycles or summary tasks); false when the event is cancelled.
removeDependency(id: string): boolean | undefined Remove a dependency.
resourceLoad(range?: { start: PlainDate; end: PlainDate; } | undefined): GanttResourceLoad[] | undefined Daily load per resource (default: the timeline range).
undo(): boolean | undefined Undo the last change (emits aui-task-change with reason ‘undo’).
redo(): boolean | undefined Redo the last undone change.

Pattern: WAI-ARIA APG Treegrid with row focus: rows carry aria-level, aria-setsize, aria-posinset, aria-expanded (summary tasks), and aria-rowindex (virtual rows); one roving tab stop. The grid is the accessible surface: every value a bar shows (dates, duration, milestone, critical, dependencies, violations, baseline variance) is text in its row. The timeline and histogram tracks are aria-hidden pointer surfaces with keyboard and toolbar equivalents for every action (WCAG 2.5.7).

The Angular component renders the framework-neutral component, so its keyboard support, roles, WCAG 2.2 criteria, budgets, and import cost apply unchanged: see Gantt Chart: Accessibility and performance.